Scrum Quiz – Scrum Certification Training – 3

Which of these is not a responsibility of the Scrum Master?

Correct! Wrong!

The time-box for the Sprint Planning meeting is?

Correct! Wrong!

Sprint Planning is time-boxed to a maximum of eight hours for a one-month Sprint. For shorter Sprints, the event is usually shorter.

Who should attend the Sprint Retrospective?

Correct! Wrong!

Which answer is not a responsibility of the Product Owner?

Correct! Wrong!

The Scrum Master is the manager for which team members?

Correct! Wrong!

Who has the final say on the order of the Product Backlog?

Correct! Wrong!

A Scrum Team uses 2 weeks Sprints and time box their Sprint Planning to 6 hours. Does this break the rules of Scrum?

Correct! Wrong!

Sprint Planning is time-boxed to a maximum of eight hours for a one-month Sprint. For shorter Sprints, the event is usually shorter.

The CEO asks the Development Team to add a "very important" item to a Sprint that is in progress. What should the Development Team do?

Correct! Wrong!

The items selected for a Sprint have been selected as most valuable with the Product Owner. The items serve the Sprint's goal. No changes should be made that endanger the Sprint Goal. No one external to the Scrum Team can force changes on the Development Team (Sprint Backlog) and the Product Owner (Product Backlog).

In Scrum, all requirements for a story should be determined before it is added to a sprint and should not change.

Correct! Wrong!

Who should attend the Sprint Retrospective?

Correct! Wrong!